LabSim Category

Practice Real SWITCH Labs with Packet Tracer

December 4th, 2012 certprepare 206 comments

The title said it all. Below are the screenshots of the lab files

Real_MLS_EIGRP.jpg

 

REAL_STP_LACP.jpg

 

Files included:

+ MLS with EIGRP lab
+ LACP – STP Lab

Download these lab files from certprepare.com

Please say thanks to Jojo who created these lab-sims. Now you can practice with real SWITCH Lab questions.

Updated:

Ghost sent me a new version of these lab files (on Apr-30-2013) which include:

+ MLS with EIGRP lab
+ LACP – STP Lab
+ VTP Lab
+ VTP 2 lab
+ STP Lab

You can download it here and please say thanks to him:

Download new updated lab files from certprepare.com

LACP with STP Sim

December 4th, 2012 certprepare 1,884 comments

Question

You work for SWITCH.com. They have just added a new switch (SwitchB) to the existing network as shown in the topology diagram.

LACP_STP_topology.jpg

RouterA is currently configured correctly and is providing the routing function for devices on SwitchA and SwitchB. SwitchA is currently configured correctly, but will need to be modified to support the addition of SwitchB. SwitchB has a minimal configuration. You have been tasked with competing the needed configuring of SwitchA and SwitchB. SwitchA and SwitchB use Cisco as the enable password.

Configuration Requirements for SwitchA

- The VTP and STP configuration modes on SwitchA should not be modified.
– SwitchA needs to be the root switch for vlans 11, 12, 13, 21, 22 and 23. All other vlans should be left are their default values.

Configuration Requirements for SwitchB

- Vlan 21, Name: Marketing, will support two servers attached to fa0/9 and fa0/10
– Vlan 22, Name: Sales, will support two servers attached to fa0/13 and fa0/14
– Vlan 23, Name: Engineering, will support two servers attached to fa0/15 and fa0/16
– Access ports that connect to server should transition immediately to forwarding state upon detecting the connection of a device.
– SwitchB VTP mode needs to be the same as SwitchA.
– SwitchB must operate in the same spanning tree mode as SwitchA.
– No routing is to be configured on SwitchB.
– Only the SVI vlan 1 is to be configured and it is to use address 192.168.1.11/24.

Inter-switch Connectivity Configuration Requirements:

- For operational and security reasons trunking should be unconditional and Vlans 1, 21, 22 and 23 should tagged when traversing the trunk link.
– The two trunks between SwitchA and SwitchB need to be configured in a mode that allows for the maximum use of their bandwidth for all vlans. This mode should be done with a non-proprietary protocol, with SwitchA controlling activation.
– Propagation of unnecessary broadcasts should be limited using manual pruning on this trunk link.

Answer and Explanation:

Read more…

MLS and EIGRP Sim

December 4th, 2012 certprepare 608 comments

Question

You have been tasked with configuring multilayer SwitchC, which has a partial configuration and has been attached to RouterC as shown in the topology diagram.

You need to configure SwitchC so that Hosts H1 and H2 can successful ping the server S1. Also SwitchC needs to be able to ping server S1. Due to administrative restrictions and requirements you should not add/delete VLANs, changes VLAN port assignments or create trunk links. Company policies forbid the use of static or default routing. All routes must be learned via EIGRP 650 routing protocol.

You do not have access to RouterC, RouterC is correctly configured. No trunking has been configured on RouterC.
Routed interfaces should use the lowest host on a subnet when possible. The following subnets are available to implement this solution:
– 10.10.10.0/24
– 190.200.250.32/27
– 190.200.250.64/27
Hosts H1 and H2 are configured with the correct IP address and default gateway.
SwitchC uses Cisco as the enable password.
Routing must only be enabled for the specific subnets shown in the diagram.

EIGRP_MLS_sim.jpg

Answer and Explanation

Read more…

VTP Lab 2

April 20th, 2012 certprepare 177 comments

Question:

Acme is a small export company that has an existing enterprise network comprised of 5 switches;
CORE,DSW1,DSW2,ASW1 and ASW2. The topology diagram indicates their desired pre-VLAN spanning tree mapping.
Previous configuration attempts have resulted in the following issues:
– CORE should be the root bridge for VLAN 20; however, DSW1 is currently the root bridge for VLAN 20.
– Traffic for VLAN 30 should be forwarding over the gig 1/0/6 trunk port between DSW1 and DSW2. However VLAN 30 is currently using gig 1/0/5.
– Traffic for VLAN 40 should be forwarding over the gig 1/0/5 trunk port between DSW1 and DSW2. However VLAN 40 is currently using gig 1/0/6.

You have been tasked with isolating the cause of these issuer and implementing the appropriate solutions. You task is complicated by the fact that you only have full access to DSW1, with isolating the cause of these issues and implementing the appropriate solutions. Your task is complicated by the fact that you only have full access to DSW1, with the enable secret password cisco. Only limited show command access is provided on CORE, and DSW2 using the enable 2 level with a password of acme. No configuration changes will be possible on these routers. No access is provided to ASW1 or ASW2.


VTP_Troubleshooting

Answer and Explanation:

Read more…

VTP Lab

April 16th, 2012 certprepare 129 comments

Question:

The headquarter offices for a book retailer are enhancing their wiring closets with Layer3 switches. The new distribution-layer switch has been installed and a new access-layer switch cabled to it. Your task is to configure VTP to share VLAN information from the distribution-layer switch to the access-layer devices. Then, it is necessary to configure interVLAN routing on the distribution layer switch to route traffic between the different VLANs that are configured on the access-layer switches; however, it is not necessary for you to make the specific VLAN port assignments on the access-layer switches. Also, because VLAN database mode is being deprecated by Cisco, all VLAN and VTP configurations are to be completed in the global configuration mode. Please reference the following table for the VTP and VLAN information to be configured:

VTP_Lab.jpg

Requirements:

VTP Domain name cisco  
VLAN Ids 20 21
IP Addresses 172.16.71.1/24 172.16.132.1/24

These are your specific tasks:

1. Configure the VTP information with the distribution layer switch as the VTP server
2. Configure the VTP information with the access layer switch as a VTP client
3. Configure VLANs on the distribution layer switch
4. Configure inter-VLAN routing on the distribution layer switch
5. Specific VLAN port assignments will be made as users are added to the access layer switches in the future.
6. All VLANs and VTP configurations are to completed in the global configuration. To configure the switch click on the host icon that is connected to the switch be way of a serial console cable.

Answer and Explanation:

 

Read more…

Spanning Tree Lab Sim

April 14th, 2012 certprepare 141 comments

Question:

The headquarter office for a cement manufacturer is installing a temporary Catalyst 3550 in an IDF to connect 24 additional users. To prevent network corruption, it is important to have the correct configuration prior to connecting to the production network. It will be necessary to ensure that the switch does not participate in VTP but forwards VTP advertisements that are received on trunk ports.
Because of errors that have been experienced on office computers, all nontrunking interfaces should transition immediately to the forwarding state of Spanning tree. Also, configure the user ports (all FastEthernet ports) so that the ports are permanently nontrunking.

SpanningTreeLab.jpg

Requirements:
You will configure FastEthernet ports 0/12 through 0/24 for users who belong to VLAN 20. Also, all VLAN and VTP configurations are to be completed in global configuration mode as VLAN database mode is being deprecated by Cisco. You are required to accomplish the following tasks:

1. Ensure the switch does not participate in VTP but forwards VTP advertisements received on trunk ports.
2. Ensure all non-trunking interfaces (Fa0/1 to Fa0/24) transition immediately to the forwarding state of Spanning-Tree.
3. Ensure all FastEthernet interfaces are in a permanent non-trunking mode.
4. Place FastEthernet interfaces 0/12 through 0/24 in VLAN 20.

Answer and Explanation:

Read more…

AAAdot1x Lab Sim

April 12th, 2012 certprepare 737 comments

Question:

Acme is a small shipping company that has an existing enterprise network comprised of 2 switches;DSW1 and ASW1. The topology diagram indicates their layer 2 mapping. VLAN 40 is a new VLAN that will be used to provide the shipping personnel access to the server. For security reasons, it is necessary to restrict access to VLAN 20 in the following manner:
– Users connecting to ASW1’s port must be authenticate before they are given access to the network. Authentication is to be done via a Radius server:
– Radius server host: 172.120.39.46
– Radius key: rad123
– Authentication should be implemented as close to the host device possible.
– Devices on VLAN 20 are restricted to in the address range of 172.120.40.0/24.
– Packets from devices in the address range of 172.120.40.0/24 should be passed on VLAN 20.
– Packets from devices in any other address range should be dropped on VLAN 20.
– Filtering should be implemented as close to the server farm as possible.
The Radius server and application servers will be installed at a future date. You have been tasked with implementing the above access control as a pre-condition to installing the servers. You must use the available IOS switch features.

AAAdot1x.jpg

 

Answer and Explanation:

Read more…